Pre-test review
Confirm drawings, calibration status, test materials, safety conditions and FAT checklist.
→Engineering / Verify / Acceptance evidence
Verification connects the approved process route to physical performance. We test equipment functions, line coordination and agreed board-output criteria before the project moves toward packing, shipment and site commissioning.
Acceptance is defined before testing begins
Factory verification route
The exact FAT scope depends on line configuration, available trial materials and the acceptance criteria agreed during Define and Engineer.
Confirm drawings, calibration status, test materials, safety conditions and FAT checklist.
→Check drives, sensors, actuators, PLC logic, interlocks and station coordination without material.
→Run agreed raw materials through feeding, forming, handling and downstream processes where practical.
→Measure factory-checkable dimensions, thickness, surface, edge condition and production stability.
→Record results, classify open items, complete retesting and approve the release condition.
→Acceptance matrix
A complete board-line FAT reviews more than machine movement. It connects mechanical, electrical and process evidence to the required finished product.
Movement, alignment, transfer, access, lubrication and maintainability.
I/O, alarms, recipes, interlocks, emergency stops and coordinated sequencing.
Feeding accuracy, mixing uniformity, forming, cutting, demoulding and sanding behavior.
Cycle time, operating speed and capacity evidence under the agreed trial conditions.
Dimensions, thickness tolerance, visual surface, edge condition and repeatability.
HMI use, adjustment points, safe access and preliminary operating guidance.
BOARD OUTPUT / 05Define what can be proven at the factory
Trial evidence is meaningful only when the material, formulation, board size, operating settings, sampling method and test duration are recorded.
Fire rating, structural performance and regulatory certification are not established by machinery FAT alone. These normally require controlled curing, representative production samples and testing by an accredited laboratory under the applicable standard.
FAT evidence package
The evidence package supports customer review, shipment release, later commissioning and technical service.
Functions, materials, settings, duration and agreed acceptance criteria.
Operating sequences, instrument readings and representative board output.
Results, tolerances, exceptions and reviewer comments.
Open points, corrective work, retest evidence, ownership and closure status.
Release decision
Verify-stage deliverables
The final package creates a transparent handoff from factory verification to logistics, installation and site commissioning.
Test scope, acceptance basis, attendees and agreed conditions.
Equipment, control, safety and line-sequence test results.
Recorded materials, settings, measurements, photos and videos.
Corrections, retest results and remaining site-stage items.
Accepted, conditionally accepted or held for further action.
Tests requiring final utilities, local materials or full site conditions.
Define verification before the test
Share your board type, formulation status, raw materials, dimensions, target capacity and quality requirements. We will define the practical FAT and commissioning acceptance route.