Engineering / Verify / Acceptance evidence

Prove the line.
Prove the board.

Verification connects the approved process route to physical performance. We test equipment functions, line coordination and agreed board-output criteria before the project moves toward packing, shipment and site commissioning.

05 — VERIFY

Acceptance is defined before testing begins

Test against an
agreed baseline.

The Verify stage uses the approved scope, materials, board specification, capacity basis and acceptance criteria—not a generic demonstration.03× levels of proof

Factory verification route

From power-up
to accepted evidence.

The exact FAT scope depends on line configuration, available trial materials and the acceptance criteria agreed during Define and Engineer.

01 / READY

Pre-test review

Confirm drawings, calibration status, test materials, safety conditions and FAT checklist.

→
02 / FUNCTION

Dry function test

Check drives, sensors, actuators, PLC logic, interlocks and station coordination without material.

→
03 / PROCESS

Material trial

Run agreed raw materials through feeding, forming, handling and downstream processes where practical.

→
04 / OUTPUT

Board review

Measure factory-checkable dimensions, thickness, surface, edge condition and production stability.

→
05 / ACCEPT

FAT & closure

Record results, classify open items, complete retesting and approve the release condition.

→

Acceptance matrix

Six dimensions
of line proof.

A complete board-line FAT reviews more than machine movement. It connects mechanical, electrical and process evidence to the required finished product.

01 / FUNCTION

Mechanical operation

Movement, alignment, transfer, access, lubrication and maintainability.

02 / CONTROL

Electrical & PLC logic

I/O, alarms, recipes, interlocks, emergency stops and coordinated sequencing.

03 / PROCESS

Process stability

Feeding accuracy, mixing uniformity, forming, cutting, demoulding and sanding behavior.

04 / CAPACITY

Output conditions

Cycle time, operating speed and capacity evidence under the agreed trial conditions.

05 / BOARD

Factory-checkable quality

Dimensions, thickness tolerance, visual surface, edge condition and repeatability.

06 / PEOPLE

Operation readiness

HMI use, adjustment points, safe access and preliminary operating guidance.

Board production line trial and output verificationBOARD OUTPUT / 05

Define what can be proven at the factory

Measure the result.
State the conditions.

Trial evidence is meaningful only when the material, formulation, board size, operating settings, sampling method and test duration are recorded.

01Trial raw materials and formulation basis
02Board thickness, dimensions and surface criteria
03Speed, cycle time and trial duration
04Sampling, measurement and acceptance tolerances
05Items deferred to commissioning or laboratory testing

Fire rating, structural performance and regulatory certification are not established by machinery FAT alone. These normally require controlled curing, representative production samples and testing by an accredited laboratory under the applicable standard.

FAT evidence package

Show what was tested.
Record what remains.

The evidence package supports customer review, shipment release, later commissioning and technical service.

01

Test scope & conditions

Functions, materials, settings, duration and agreed acceptance criteria.

02

Photos, video & samples

Operating sequences, instrument readings and representative board output.

03

Measurement record

Results, tolerances, exceptions and reviewer comments.

04

Issue & retest log

Open points, corrective work, retest evidence, ownership and closure status.

Release decision

Verification ends
with a clear status.

01Critical safety and functional items passed→
02Agreed FAT criteria reviewed with the customer→
03Open items classified, owned and dated→
04Shipment, conditional release or retest status recorded→
05Commissioning-only tests transferred to the site plan→

Verify-stage deliverables

What the customer
receives before shipment.

The final package creates a transparent handoff from factory verification to logistics, installation and site commissioning.

OUTPUT / 01

Approved FAT protocol

Test scope, acceptance basis, attendees and agreed conditions.

OUTPUT / 02

Functional test record

Equipment, control, safety and line-sequence test results.

OUTPUT / 03

Trial-board evidence

Recorded materials, settings, measurements, photos and videos.

OUTPUT / 04

Issue closure register

Corrections, retest results and remaining site-stage items.

OUTPUT / 05

Shipment release record

Accepted, conditionally accepted or held for further action.

OUTPUT / 06

Commissioning test plan

Tests requiring final utilities, local materials or full site conditions.

Define verification before the test

Tell us what the line
must prove.

Share your board type, formulation status, raw materials, dimensions, target capacity and quality requirements. We will define the practical FAT and commissioning acceptance route.